This
inscription is written to be a general guidelines for site rotating engineer to
inspect the foundation prior equipment erection/installation.
After
the civil team finish with the concrete pouring activity, it is recommended for
the civil team to make Foundation Work Release Notice or Foundation Handover from
civil to mechanical rotating. There are several items that the mechanical team
should give some attention to, prior accepting the foundation, which will be
discussed further below.
Foundation Handover Document
This
handover document is necessary to keep the split of responsibility between the
civil and mechanical team. For example, if there is still defect found prior to
handover to mechanical team, then it is still the civil responsibility to
repair the defect. Then, to identify whether the foundation is defectless or
not, the mech rotating team should do two kinds of inspection, which are:
1.
Foundation
centerline inspection
This
inspection is generally the same with the pre-pouring concrete inspection. To
help with the inspection, I recommend to use a simple string/wire to mark the
location.
The items that needed to be concerned with are:
- The coordinate of the foundation centerline
- The size of the foundation (length, width, diagonal)
- The elevation of the TOC (top of concrete)
- The size of the anchor box (length, width, depth)
- The relative position of the anchor bolt
- The elevation of the anchor bolt (if using embedded anchor)
2.
Padding
plate and Anchor Elevation check
This
inspection adjective is to check the padding plate position and level, the
tools that usuallty used in this inspection is an Auto Level Topcon. The items
that needed to be concerned with are:
- The elevation of padding plate is correct and within tolerance (+-3mm)
- The padding plate height shall not exceed 100mm relative from the Top Of Concrete
- The position of the skid is need to be considered during the setting position of the padding plate
If
there are any defects found during these two inspection, then it is still the
civil responsibility to repair it. After
both of the inspections are finish, then the foundation is good to go.
The Foundation Handover Document pre-requisite documents are as follows :
The Foundation Handover Document pre-requisite documents are as follows :
1. Pre-Pouring
Inspection Report
2. Concrete
Compressive Test Report
3. Foundation
Centerline Inspection Report (witnessed by mech rotating team)
4. Padding
Plate and Anchor Elevation Check Report (witnessed by mech rotating team)
Please
be aware that the common curing time for concrete is 28 days, so the equipment
can be installed after 28 days, unless the civil team were using curing additive
to their concrete mix. After Foundation Handover Document is signed by both
parties (civil & mech rotating) then we can continued to prepare the next step.